Milestones

  • The Earls Court Development Company is born

    December 2019

     

    -

     

    Complete

    Working together with Delancey (on behalf of its client funds including the Dutch pension fund manager, APG) and Transport for London (TfL), the joint venture called The Earls Court Development Company (ECDC) is born.
  • Housing Estates returned to Council ownership

    Summer 2020

     

    -

     

    Complete

    West Kensington and Gibbs Green housing estates are returned to the ownership of Hammersmith & Fulham Council. The estates will not be included in our future plans for the site.
  • Initial online surveys

    Summer 2020

     

    -

     

    Complete

    Initial online surveys through Commonplace asking local people what they want to see and what meanwhile uses they would like to see on the site.
  • Community Hub

    June 2021

     

    -

     

    Complete

    Drop-in sessions are organised with the local community on plans to repurpose the former replacement homes suite on Aisgill Avenue into a new temporary Community Hub.
  • 344-350 Old Brompton Road gets green light

    July 2021

     

    -

     

    Complete

    The Royal Borough of Kensington & Chelsea gives the green light for the redevelopment of 344-350 Old Brompton Road
  • London Wonderground launched

    July 2021

     

    -

     

    Complete

    London Wonderground launched on the EC2 site and the Pleasure Garden opened on Warwick Road Apron, opposite Earl’s Court Underground station. You can find more about other ways the site has been opened up on the latest news page.
  • Earls Court Community Fund launched

    July 2021

     

    -

     

    Complete

    Launch of the Earls Court Community Fund with £180,000 committed this year. For more details visit https://theearlscourtdevelopmentcompany.com/news-events/the-launch-of-the-earls-court-community-fund.
  • Our emerging vision

    December 2021

     

    -

     

    Complete

    Survey launched to help us shape the plans to bring the Earls Court site back to life.
  • Consultation on early concepts to 'bring the wonder back to Earls Court'

    June 2022

     

    -

     

    Complete

    During the previous phase of consultation we ask you how we could bring back the wonder to Earls Court. This phase responds to that feedback, introducing some initial concepts for feedback.
  • Underbelly returns to Earls Court

    June 2022

     

    -

     

    Complete

    For the second consecutive summer, the Underbelly production transforms the EC2 site into a seasonal playground with a free open-air cinema and city beach.
  • Welcome, The Lost Estate!

    July 2022

     

    -

     

    Complete

    The immersive theatre group The Lost Estate has set up home in Earls Court in the former Mannequin Factory adjacent to West Kensington tube station. Their first performance – ‘The Great Christmas Feast’ – will launch in the winter.
  • An artist-in-residence is coming to Earls Court

    September 2022

     

    -

     

    Complete

    An open call to artists has been issued by The Earls Court Development Company to launch a rolling residency that will see portraits of the local community commissioned.
  • Designing the draft masterplan

    September 2022

     

    -

     

    Complete

    Conversation Corner has re-opened to showcase the priorities and asks received from the community during the most recent phase of engagement this summer.
  • Local groups receive £180,000 funding

    September 2022

     

    -

     

    Complete

    Eighteen local charities and organisations have been selected to receive grants from the £180,000 Earls Court Community Fund.
  • Lillie Bridge Depot purchased

    November 2022

     

    -

     

    Complete

    Earls Court Partnership Limited has completed the purchase of Lillie Bridge Depot and associated land from Transport for London. The land is a key later phase of the future development.
  • Phase 1 architects announced

    November 2022

     

    -

     

    Complete

    Following a series of design competitions over the summer, a number of architecture practices have been appointed to deliver the first phase of the development. The successful practices are Sheppard Robson with Series Architects and drMM, ACME, Haworth Tompkins and Maccreanor Lavington.
  • Masterplan unveilling

    February 2023

     

    -

     

    Complete

    The launch of the latest round of engagement activity following the initial proposals for the Earls Court site being shared.
  • Updated Masterplan

    November 2023

     

    -

     

    January 2024

    Showing the evolution of our draft masterplan in response to feedback.
  • Phase One designs

    March 2024

     

    -

     

    In Progress

    Revealing the latest designs for our first phase of development